Civil Engineer
2016-07-31 - Presently working
Handling all work related to Piping – Job planning, MTO preparation from isometrics & support drawings, Loop marking & loop files preparation, Joint & spool marking, Spool management, Fit up, welding, DPR Submission & progress review, Line Dismantling, erection & installation, Sub contractor`s work measurement certification, Daily TBT & Safe work practices at work place.
Generating reports from Joint Master & Spool Master Sheet.
Piping Fabrication of 1.02 Lakh ID (Including 23000 ID of P5 AS Welding).
Scope preparation for Pre Turn around & Turn around Job, Tie Joints marking & Identification & completion at Site.
Erection & Mechanical Clearance of Transfer Line in VDU.
Punch list preparation & liquidation, Mechanical Clearance of Loops & System Handover to Owner. Golden Joints Completion for CDU VDU Shut Down Project.
Work Scope- 1.5 Lakh ID Welding & 1.7 Lakh IM erection (Pre TA- 1.2 Lakh ID & TA- 30000 ID)