Activities Performed:
• Quality maintain according to drawing and specification.
• Supervision of 90 mm to 160mm dia. HDPE pipe laying work.
• Supervision 400mm Dia. Clear Water Rising Main Pipe Laying work.
• Supervision of Raw Water Rising Main 600 Dia. K-9 Pipe Laying work.
• Testing of material, Cube Test, Impact Value Test, Sieve Test, Water Absorption Test, and
Slump Test done at lab at field time to time.
• Supervision of BT Road Restoration and CC road restoration work.
• Supervision of OHTs of 100KL to 465KL work.
• Supervision of 6.75 MLD WTP.
• Supervision of 77.88 Intake well.
• Strictly monitor the progress of work for timely completion of the project.
• Prepared contactor’s and consultancy’s bill.
Keep proper records of the Contractor’s activities and work progress.